Port Everglades sand trap: Broward adds $1.35 million while dredging stays paused over damaged coral
Nov 16, 2026
On Tuesday, Nov 10, 2026, the Broward County Commission voted 9-0 to approve a third amendment to its dredging contract with Great Lakes Dredge & Dock for the Port Everglades Sand Bypass Project (item 26-1270). The amendment adds $1,352,661, for a not-to-exceed total of $62,800,477, to pay for dredged quantities that came in above the original estimates. The county says the dredging is about 94% complete.
The project is digging a 10.8-acre sand trap on the seafloor just north of Port Everglades Inlet. The idea is to catch sand drifting south along the coast, then periodically move it across the inlet to Broward's beaches to the south. The county expects to move about 100,000 to 225,000 cubic yards in each bypass event, every two to four years.
The work has been stopped since summer. After a planned July to October pause for coral spawning, Miami Waterkeeper, the Center for Biological Diversity, the Florida Wildlife Federation and the Diving Equipment and Marketing Association, represented by Earthjustice, sued the Army Corps and the National Marine Fisheries Service in early August. Days later, in an Aug 7 letter, the Corps said underwater surveys showed the project may have exceeded the harm its permit allowed to threatened staghorn coral (the permit estimated 125 colonies). The Corps reopened its Endangered Species Act review and agreed no dredging is authorized until that review is done, and not before November 2026 at the earliest. We found no public notice yet that the review has finished. At the Nov 10 meeting, Miami Waterkeeper urged stronger monitoring of sediment plumes and nearby reef.
Why this matters for the beach animals: this fight is about the reef offshore, but the sand caught in the trap will end up on the swash zone where sand fleas (mole crabs), coquinas and ghost crabs live. Sand trapped from the same coastline is more likely to match the native beach than many offshore or inland sources, and grain size and shell content are what research ties to how fast these animals recover (see the right sand). But the county hasn't published the grain size of the trapped sand, and nothing we found requires counts of beach animals before and after each bypass event.
Questions for Broward County's Resilient Environment Department:
- What grain size and shell content does the sand in the trap have, compared with the receiving beaches south of the inlet, and will those test results be published?
- Will each bypass event include before-and-after counts of mole crabs, coquinas and ghost crabs next to an untouched control beach?
- Will bypass events be scheduled and phased so placed stretches can recolonize from nearby untouched beach?
Full details are in the Project Tracker. Want to ask these questions yourself? Take action.
Sources
- Broward County agenda item 26-1270, Third Amendment to Agreement PNC2126890C1 (Nov 10, 2026)
- Citizen Portal: Broward approves Port Everglades sand-bypass amendment despite coral-monitoring concerns (Nov 10, 2026)
- Miami Waterkeeper: Corps temporarily halts Fort Lauderdale dredging project after conservationists' lawsuit (Aug 13, 2026)
- WLRN: Army Corps halts work on giant 'sand trap' near Port Everglades after finding damaged coral (Aug 12, 2026)
- Tryphe: Port Everglades Sand Bypass $62.8M contract amendment (bypass volumes and schedule)