Ponte Vedra Beach: 805,000 more cubic yards planned, two years after a 2-million-yard rebuild

Nov 18, 2026

On Nov 17, 2026, the St. Johns County Commission approved, 5-0 on its consent agenda, a $3,624,521.62 contract with First Line Coastal LLC to design, permit and oversee construction of the FEMA Category G Ponte Vedra Beach Restoration Project. It repairs damage from Hurricane Milton (FEMA disaster DR-4834).

The contract says the intent is "to place 805,000 cy of sand somewhere between R25-R46.2." R-25 and R-46.2 are state beach survey markers; R-46.2 is the northern edge of the Guana Tolomato Matanzas National Estuarine Research Reserve. The exact spots and design are still to be worked out. The sand itself will be placed under a separate construction contract, and no construction date or cost has been published.

This beach was just rebuilt. The county finished a $38.6 million project in July 2024 that placed more than 2 million cubic yards along about nine miles, from the Duval County line to the Guana reserve. Milton hit three months later. Because the rebuilt beach was damaged in a declared disaster, FEMA is paying for the repair.

It's the third sand project on the St. Johns County coast we've covered this month. The same consultant team is on the county's FEMA job at South Ponte Vedra Beach, south of the reserve, and the Army Corps' 50-year South Ponte Vedra project just moved into design (our Nov 17 post).

Why this matters for the beach animals: sand fleas (mole crabs), coquinas and ghost crabs live in the top layer of sand. In one North Carolina study they were 86 to 99% lower 5 to 10 weeks after sand placement, and a New Jersey study found mole crab biomass fell about 90% (see the science and our post). How fast they come back depends on how closely the new sand matches the old beach in grain size and shell content (the right sand) and on how much time passes between placements. If this repair is built in the next year or two, parts of this beach could get new sand twice in about four years. The design and permitting phase that just started is when sand specs, timing and monitoring get decided.

Questions for St. Johns County (Purchasing, 904-209-0158, or the coastal projects office, coastalprojects@sjcfl.us):

  1. Which borrow area will the 805,000 cubic yards come from, and will the county publish how its grain size and shell content compare with the native Ponte Vedra Beach sand?
  2. Will the design and permits require before-and-after counts of mole crabs, coquinas and ghost crabs next to an untouched control beach, and did the 2024 project's monitoring show how fast they recovered?
  3. Will placement be limited to the stretches that actually lost sand, and phased so placed areas can recolonize from untouched beach nearby?

Full details are in the Project Tracker. Want to ask these questions yourself? Take action.