Anna Maria Island: up to 1.1 million cubic yards of offshore sand on 5.5 miles of beach
Nov 10, 2026
Anna Maria Island's next big sand job is scheduled to start this month. The U.S. Army Corps of Engineers Jacksonville District awarded Marinex Construction of Charleston, South Carolina, a firm fixed-price contract (W912EP-26-C-A028) to rebuild about 5.5 miles of beach and dune on the island in Manatee County. The Defense Department announced $28.4 million obligated at award, with a total face value of $32,373,000. Five companies bid.
- Where: the federal Central Beach Segment, from about 79th Street North in Holmes Beach to 5th Street South in Bradenton Beach, plus Cortez Beach and Coquina Beach, according to Manatee County.
- How much sand: about 900,000 cubic yards in the base contract and about 200,000 cubic yards more at Coquina Beach as an option, according to the Corps solicitation (W912EP26BA010). The county's natural resources director told the AMI Sun that about 1 million cubic yards will be added, on top of about 6 million cubic yards placed in six renourishments since 1992.
- Where it comes from: dredged from designated offshore borrow areas in the Gulf and pumped onto the beach.
- When: the county schedule is November 2026 through March or April 2027. The contract allows 240 calendar days after notice to proceed, with estimated completion by May 28, 2027.
- Who pays: the Corps covers nearly all of the federal segment. Manatee County advanced $6.18 million in tourist tax money for the Cortez and Coquina work, which it expects FEMA (75%) and the state (12.5%) to largely repay. The state's share for the project, $7,012,228.50, was listed as pending execution in FDEP's latest funding status report.
- Monitoring in the scope: beach tilling, vibration monitoring, "environmental monitoring" and dune planting. The public documents we found don't publish the grain size of the borrow sand or say which animals will be monitored.
Sea turtles get real attention here: Anna Maria Island Turtle Watch relocated 42 nests ahead of the smaller Coquina Beach project this summer. Nobody has announced a count of the sand fleas (mole crabs) and coquinas that live in the swash zone and feed sanderlings, willets and surf fish. In one North Carolina study, these animals were 86 to 99% lower 5 to 10 weeks after sand placement, and the authors pointed to poorly matched grain size and shell content as a likely cause (see the science). Placing about a million cubic yards between November and spring means the beach will be recovering going into the 2027 shorebird and turtle season.
Questions for the Corps and Manatee County:
- How closely does the offshore borrow sand match native Anna Maria Island sand in grain size and shell content, and will the test results be published?
- Will the "environmental monitoring" include before-and-after counts of mole crabs, coquinas and ghost crabs next to an untouched control beach?
- Can placement be phased so each stretch can recolonize from untouched beach nearby before the next one is buried?
Full details are in the Project Tracker. Want to speak up? Take action.
Sources
- DredgeWire: Marinex awarded $28.4M Anna Maria Island contract (DoD announcement, Sep 14, 2026)
- SAM.gov solicitation W912EP26BA010 and bid abstract (SweetSpot copy)
- Manatee County news release (Jun 17, 2026)
- AMI Sun: County Commission approves $6.18 million (Jun 22, 2026)
- AMI Sun: First of two beach renourishment projects starts soon (Jul 7, 2026)
- FDEP FY2026-27 Q1 Beach Appropriation Status Report